Date:June 19th,2024

Chief Executive Officer

Subject: Response to Notice ofFraud and Critical WTG Serial Defects & Equipment Defects at the 60MW WindPower Project

Reference: Employer’s letter with reference number-

Dear Sir,

We,, the Contractor and theSupplier, have meticulously reviewed the notice issued by  (the “Employer”) and were acutely aware of the severity of theissues raised from the initial notification, since then, the Supplier and theContractor initiated appropriate actions promptly and coordinated with OEM ofWTG equipment. Despite engaging in multiple discussions with SEnergy (Private) Limited, we regret to be informed that000 has yet presented a final investigationplan ( as Attachment 1 000’s reply dated June 18th, 2024). Followingthe 000s reply, an immediate escalation of the matter internally within 000has been actioned, accompanied by insistence on an urgent and thoroughresponse. A senior-level intervention is being implemented to ensure 000 fullycomprehends the gravity of the situation and promptly delivers a comprehensiveinvestigation strategy.

Meanwhile,as Parent Company of the Supplier and the Contractor, we hereby commit that ourteam will conduct a thorough, independent and transparent investigation timelywith OEM and Employer team to determine the root cause of all mentioned issuesand further actions required within a reasonable timeline. 

Following the Employer’s demand in letter dated June16th, 2024, our point wise reply is as hereunder:

identify the AuthorizedPersons & Communication Plan

As required,Mr. xxx as xxx of the Parent Companywilltake the lead in the resolution process outlined in the Employer’s notice withthe support of a complete professional team from our company and OEM, who isresponsible for decision-making, implementation, oversight and communicationwith Employer team.

For timely coordination and communication among parties, in the interest of maintaining transparency andefficiency, we pledge to regularly update xxx on theprogression of our dialogues with xxx on weekly basis. This encompassessharing any preliminary findings or updates pertaining to the investigationplan as soon as they are available.

Recognizing the significance of open communication channels andeffective cooperation, we will establish a dedicated task force to work closelyalongside your representatives and xx with the objective of accelerating theresolution process.

Thorough Investigation

Wehereby commit that our team will conduct a thorough, independent andtransparent investigation timely with OEM and Employer team to determine theroot cause of all mentioned issues and further actions required within areasonable timeline. It’s kindly requested the Employer to grant an extendedtimeline for xxx and our company to prepare a detailed and comprehensive planto conduct the investigation.

Remedial Plan

Upon conclusion of the investigation, we are committed to implementing all necessary remedial measures in line with the findings. It’s reasonable to have investigation first, then we make a practical and satisfying remedial plan. We request for your kind understanding and support on the plan preparation.

Warranty Period Extensionand Warranty Bond Extension

Currently, the offshore warranty bond is validtill January 31,2025, andthe onshore warranty bond is valid till July 31,2024. Once the investigation ofall issues raised in the Employer’s notice is completed with conclusion, theEmployer, the Contractor and the Supplier shall have a specific discussion forthe Warranty Period and Warranty Bond in line with the investigation findings.

Independent PerformanceTesting

Our contractual obligations are toensure the compliance of the equipment and “Fit for Purpose”. The Contractorand the Supplier will strictly follow and comply with its obligations under theContracts. It’s recommended to have comprehensive investigation first, then itwould be clear whether taking any further independent performance testing isnecessary.

For the issues raised by the Employer for all mentioned defects, the Supplier and the Contractor will try the best to engage all stakeholders and carry out the comprehensive investigation to have the final conclusion and work out any reasonable and applicable remedial plan.

Weare deeply concerned about the implications of these issues on our partnershipand remain steadfast in our determination to restore faith in our capability tofulfill our obligations. And we fully understand the seriousness of thisincident and will do our utmost to ensure that all issues are properly handled.

Yours faithfully,

For and on behalf of 

___________________________

 

 

 

 

xxxxx

Project Director

相关文章

  • 老家的梨

    上午给市雷霆办回复了一份函件,然后给社区布置了非公企业团建的工作,再把盖好公章的函件送到了市雷霆办,顺便去龙潭社区...

  • 被批评

    今天在家加班加到10:30,可是却被一个领导批评了。 因为他的一个项目回复的函件,他说我写的太马虎。也确实是白天事...

  • 语言

    今早突然感知到语言的缺陷性。 日常工作中起草函件,为了把话说的完整全面都要找很多字词修饰,以便全集完整,子集分条处...

  • Java关键字解析——Java基础回炉(四)

    前言 本文是深入Java基础系列的第四篇,关于文集介绍可通过<>进行了解。 这篇文章...

  • [转题](http://blog.csdn.net/xunyn/

    多数是CocoaTouch社区的回复,其中蓝色字体是我的补充 iOS题系列: iOS如何面试iOS基础面试题(一)...

  • 宁乡老街函件

    需甲方确认的内容 1.建筑 a.建筑层高及总高度控制 b.人防部门的设计要点 c.空调设备形式 d.绿色植被种类是...

  • Everyone has his misery.

    Everyone has his misery. 在知乎上读了不少故事,关于童年阴影,关于外貌缺陷,关于性格缺陷,...

  • 2020-05-21

    关于缺陷与悲哀

  • 《软件测试技术经典教程第二版》阅读笔记5

    第一部分 软件测试基础 第 5 章 缺陷管理 本章要点: ● 了解Bug的分类,缺陷报告模板,以及提交缺陷...

  • 在黄岛装修,墙面打磨不好毁了全部的效果,多么痛的领悟

    昨天有一个工地出问题了,业主给我打电话说顶面不平,这是一个最近刚刚做完的工地,基础装修已经全部结束了,业主已经...

网友评论

      本文标题:2024-06-19 关于回复业主系列缺陷的一个基础函件

      本文链接:https://www.haomeiwen.com/subject/caafcjtx.html